Question: Using the information below, determine the job lateness for SPT . Job Processing Time ( days ) Due Date ( days ) A 4 1

Using the information below, determine the job lateness for SPT.
Job
Processing Time (days)
Due Date (days)
A
4
11
B
6
5
C
3
1
D
2
8
E
5
7