Question: Using the information below, plot out a full Network Diagram of the two projects and: I. identify the Critical Path of each Project II. how

Using the information below, plot out a full

Using the information below, plot out a full Network Diagram of the two projects and: I. identify the Critical Path of each Project II. how many days does it take to complete each Project For Project A (5 marks) For Project B (5 marks) (2x5=10 marks) Activity Activity Project a Preceding activity None A B Project b Preceding activity None Activity duration 2 4 Activity duration 2 4 B A B C B 3 C 3 D B 5 D B 5 E 7 E B 4 F 4 F 4 G 6 B CD DE F,G H H G C,D D,E F,G . 6 H H J K 3 5 3 5 J 8 L J 2