Question: Using the information from a project below: Activity Predecessor A B C D E F G 3.1 3.2 3.3 A;B B;C D;E F Duration
Using the information from a project below: Activity Predecessor A B C D E F G 3.1 3.2 3.3 A;B B;C D;E F Duration (Days) 10 9 13 15 17 18 10 Construct the network diagram (AON) and identify the Critical Path. (10) Calculate the Early Start; Late Start; Early Finish & Late Finish for all activities. Compute the 'slack" time for each activity. (10) (5)
Step by Step Solution
3.44 Rating (151 Votes )
There are 3 Steps involved in it
Answer Lets break down the tasks one by one 31 Construct the network diagram AON and identify the Critical Path Heres the ActivityonNode AON network d... View full answer