Question: Using the information in Table 1, assuming that the project team will work a standard working week (5 working days in 1 week) and that

Using the information in Table 1, assuming that

Using the information in Table 1, assuming that the project team will work a standard working week (5 working days in 1 week) and that all tasks will start as soon as possible. Task Description Duration (Working Days) Predecessor/s A Requirement Analysis 5 B Systems Design 15 A C Programming 25 B D telecoms 15 E Hardware Installation 30 F Integration 10 G System Testing 10 H Training/Support 5 1 Handover and Go-Live 5 Calculate the paths of this project Find and explain the critical path of the project 4.1 4.2 B B C, D E, F G H (15)