Question: Using the information in the following table, determine how much of the supply variance is due to a change in volume. Budgeted Actual Variance Volume
Using the information in the following table, determine how much of the supply variance is due to a change in volume.
Budgeted Actual Variance
Volume 1,000 1,100 100
Supplies $10,000 $12,750 $2,750
Cost per Unit 10 11.60 1.60
A. $900
B. $1,000
C. $1,050
D. $1,250
E. $1,500
Step by Step Solution
There are 3 Steps involved in it