Question: Using the information provided in the table below, find the probability of completing the project in 46 weeks? Activity Immediate Predecessor(s) Optimistic Time Estimate (weeks)

Using the information provided in the table below, find the probability of completing the project in 46 weeks?
Activity Immediate Predecessor(s) Optimistic Time Estimate (weeks) Most Likely Time Estimates (weeks) Pessimistic Time Estimates (weeks)
A none 3 6 9
B A 3 5 7
C A 4 7 12
D B, C 4 8 10
E B, C 9 12 18
F D 5 10 13
G E 3 6 8
H F 1 5 12
I G 7 8 9
J H, I 3 3 3