Using the information provided in the table, the network diagram and the project completion time = 25
Fantastic news! We've Found the answer you've been seeking!
Question:
Using the information provided in the table, the network diagram and the project completion time = 25 weeks, reduce the completion time of the project by 3 weeks in the most economical way.
Activity | Normal Time (weeks) | Normal Cost ($) | Crash Time (weeks) | Crash Cost ($) | Maximum weeks Reduced | Crash Cost per Week ($) | ||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|
A | 3 | 500 | 2 | 900 | 1 | 400 | ||||||
B | 4 | 600 | 3 | 700 | 1 | 100 | ||||||
C | 6 | 800 | 3 | 1,307 | 3 | 169.00 | ||||||
D | 6 | 1,500 | 4 | 2,150 | 2 | 325 | ||||||
E | 6 | 1,750 | 4 | 2,250 | 2 | 250 | ||||||
F | 5 | 1,200 | 5 | 1,200 | 0 | 0 | ||||||
G | 7 | 1,500 | 5 | 1,808 | 2 | 154 | ||||||
H | 3 | 500 | 3 | 500 | 0 | 0 |
Reduce G byselect a number of weeks 1203 week(s), C byselect a number of weeks 2014 week(s), at a cost of $enter a dollar amount .