Question: Using the information provided in the table, the network diagram and the expected project completion time = 3 9 ?weeks: Activity Optimistic Time ( weeks

Using the information provided in the table, the network diagram and the expected project completion time =39 ?weeks:
Activity
Optimistic Time
(weeks)
Most Likely Time
(weeks)
Pessimistic Time
(weeks)
A
81012
B
41016
C
456
D
6810
E
4712
F
679
G
4812
H
333
A network diagram is shown for activities A to H. ?There are four paths. Path one is A, ?B, ?D, ?F, ?H. ?Path two is A, ?B, ?D, ?G, ?H. ?Path three is A, ?C, ?E, ?G, ?H. ?Path four is A, ?C, ?E, ?F, ?H.
The critical path is A-B-D-G-H.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!