Question: Using the information provided in the table, the network diagram and the project completion time = 2 5 weeks, reduce the completion time of the
Using the information provided in the table, the network diagram and the project completion time weeks, reduce the completion time of the project by weeks in the most economical way.
tableActivitytableNormalweekstableNormalCost $tableCrash TimeweekstableCrashCost $tableMaximumWeeksReducedtableCrash Costper Week $ABCDEFGH
If there is no amount for a box enter All boxes must be filled.