Question: Using the knowledge and skills you've learned to date about estimating time, build a schedule for the project scope and WBS that you produced in
- Using the knowledge and skills you've learned to date about estimating time, build a schedule for the project scope and WBS that you produced in an earlier assignment.
- To build your schedule, decompose your WBS into activities and follow the PMBOK scheduling sequence.
- Ensure your schedule has all the estimated activities and durations, are logically sequenced, milestones defined, with a minimum of 30 activities in the schedule, and no activities longer than 15 days in duration.
- You also need to ensure your critical path is specified by activity (not WBS). Remember, activities are contained WITHIN the WBS; they are not the WBS.
-Do not make anyone guess the critical path; it should be well graphed and stated on a Gantt-type chart. I would suggest that you make all critical activities red, that way we can all tell what activities are critical. -Note that you can use any scheduling software you would like: MS Project 2019, MS Excel, Ganttner, or other scheduling software you have access to that will create a Gantt chart.
This is my previous project, please use this information to answer questions listed above!
The project that I went with is to develop a new mobile app for a fitness studio. This app will allow customers to book classes, access instructionals content and be able to track their workouts. It will also help the studio streamline their class booking and provide value to their customers.
Success Criteria
1 App development and launch on both IOS and and Android platforms.
2 App must be user-friendly and meet all requirements specified in the project scope statement as listed.
3 The app must integrate with the studios existing booking system.
4 App must be tested and function properly without any major bugs or issues.
5 The app must also result in increased customer engagement and retention.
Project Boundaries In Scope (Inclusions) / Deliverables User-friendly interface.
Integration with the studios existing booking system
Instructional content for users.
Basic user tracking and workout logging. Development and launch of mobile app for a fitness studion.
Not In Scope (Exclusions)
Providing payment processing on the app.
Advanced workout tracking and data analytics.
Integration with third-party fitness tracking apps.
Developing a web application overall.
Assumptions:
A1 The studios existing booking system can be integrated using the mobile app. The app may not function properly without integration.
A2 The app will be popular with customers and lead to increased engagement and retention overall. The studio may not see significant benefits from the app.
A3 The app will be approved and released on both IOS and Android stores. The app may only be released on one platform or not at all.
A4 Development will be completed within budget and timeline. The project may not be completed within budget and timeline constraints.
Constraints:
# Constraint: Imposed by:
C1 Development budget is $50,000 - Finance Department
C2 The app must be compatible with existing studio software - IT Department
C3 App must also comply with both IOS and Android - App Store Policies C4 Development timeline is 6 months - Executive Management
Risks:
Action R1 Poor user adoption of the app conduct market research and user testing before the launch.
R2 Technical issues during development perform regular testing and have contingency plans in order.
R3 Changes in app store policies that impact app development stay up to date on app store policies and make adjustments as needed.
R4 Inadequate resources for development and considering outsourcing development or reevaluating budget and timeline deadlines.
R5 Competition from other fitness apps who offer unique features and values to customers.
Functional Organizations Involved:
Organization - Participation
IT Department - App Development and Integration
Fitness Studio Management - Project Sponsor
Marketing Department - App Promotion and User Acquisition
Project Milestones # Milestone Description Date Critical Dependencies
1 Project Kick-Off 05/30/2023 None
2 App Design and Requirements 06/16/2023 None
3 App Development Begins 07/02/2023 Milestone 2
4 Beta Testing Begins 11/01/2023 Milestone 3
5 App Launch on IOS and Android 01/02/2024 Milestone 4
6 Project Hand-off 01/15/2024 Milestone 5