Question: Using the Material Requirements Planning ( MRP ) report below, why are only 1 2 9 units of G 2 8 3 7 ordered?Answer choice
Using the Material Requirements Planning MRP report below, why are only units of G ordered?Answer choice below:
There is onhand inventory of units to use up
There is a scheduled receipt of units of Item G in Period
They are needed to produce Item E
All of the above determine this quantity