Question: Using the Network Diagram below, describe the relationships between each activity pertaining to lags. Notes: Ensure you use proper terms such as Start and Finish
Using the Network Diagram below, describe the relationships between each activity pertaining to lags.
Notes:
- Ensure you use proper terms such as "Start" and "Finish"
- Assume the lags are referring to "days"
- Activities can have multiple relationships
| Activity | Lag Description |
| F | Cannot start until Activity A finishes Cannot finish until 2 days after Activity E finishes |
| E | |
| D | |
| C | |
| B |
0 O 0 A Design system 5 Lag 3 ES SL LS 3 0 3 5 5 10 B Order hardware 1 Legend ID EF Description SL Duration LF 0 4 Lag 4 8 C 0 8 Install hardware 2 10 0 10 10 O Lag 2 01 12 D Install software 10 6 4 16 16 0 5 16 11 16 E Test system 2 F System documentation 3 17 0 17 Lag 1 19 0 19 Lag 2
Step by Step Solution
There are 3 Steps involved in it
From the information provided in the image and the accompanying table here are the relationships bet... View full answer
Get step-by-step solutions from verified subject matter experts