Question: Using the NPV method (Net Present Value), Please use a 10% discount rate. Define the technique. Discuss the difference between this method and the pay
Using the NPV method (Net Present Value), Please use a 10% discount rate.
Define the technique.
Discuss the difference between this method and the pay back and discounted pay back method.
Use a 10% discount rate.
Remember to carry out your answers at least two decimal places.
| Year | Project A | Project B | Project C | |
| 2018 | ($3,000,000) | ($3,000,000) | ($3,200,000) | |
| 2019 | $0 | $975,000 | $985,000 | |
| 2020 | $600,000 | $975,000 | $925,000 | |
| 2021 | $900,000 | $975,000 | $1,000,000 | |
| 2022 | $3,000,000 | $1,000,000 | $950,000 | |