Question: Using the PERT method, estimate the duration of the project for fulfilling the activities A through H: 1- what would be project duration given that
Using the PERT method, estimate the duration of the project for fulfilling the activities A through H:
1- what would be project duration given that the activities are fulfilled in sequence starting with Activity A and ending with activity H?
2- What would project duration be if the durations are based on the optimistic estimate?
What would project duration be if the durations are based on the pessimistic estimate?

POST IN EXCEL
Name: Project Delta Durations are listed in weeks Activity Optimistic Most Likely Pessimistic A 3 4 11 2 5 8 M 0 3 6 9 Description Contract signing Questionnaire design Target market ID Survey sample Develop presentation Analyze results Demographic analysis 8 12 20 I on Mono 3 5 12 2 4 7 G 6 9 14 Presentation to client 1 2 4Step by Step Solution
There are 3 Steps involved in it