Question: Using the PERT method sample file uploaded, follow the method outlined in the .pdf file and PPT to complete the schedule with 95% confidence level.

Using the PERT method sample file uploaded, follow the method outlined in the .pdf file and PPT to complete the schedule with 95% confidence level.

Find the Z value for 95% confidence level in pdf file containing the z table.

Upload your completed excel file hereUsing the PERT method sample file uploaded,

Example Time Estimates (in weeks) for a Project / Cost estimates in $ MOST OPTIMISTIC LIKEL PESSIMISTIC EXPECTED TIME Y VARIANCE ACTIVITY a m b t = (a + 4m + + b)/6 [(b a )/6] A 1 2 3 2 0,111111111