Question: Using the PERT three - estimate approach, the three estimates for one of the activities of a project are as follows: optimistic estimate = 3
Using the PERT threeestimate approach, the three estimates for one of the activities of a project are as follows: optimistic estimate days, most likely estimate days, pessimistic estimate days. What are the resulting estimates of the mean and variance of the duration of the activity?
Mean: Select
Variance: Select
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
