Question: Using the PERT three - estimate approach, the three estimates for one of the activities of a project are as follows: optimistic estimate = 3

Using the PERT three-estimate approach, the three estimates for one of the activities of a project are as follows: optimistic estimate =30 days, most likely estimate =36 days, pessimistic estimate =48 days. What are the resulting estimates of the mean and variance of the duration of the activity?
Mean: [ Select ]["42","37","34","36"]
Variance: [ Select ]["12","9","13","3"]

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!