Question: Using the predictive approach, how should customer change requests be handled? Implement customer change requests right away Use a change control process to address the

Using the predictive approach, how should customer change requests be handled? Implement customer change requests right away Use a change control process to address the requests Record the change requests in the product backlog in order to implement them Extend the entire project schedule to implement change requests