Question: Using the priority list T 4 , T 6 , T 5 , T 7 , T 8 , T 2 , T 1 ,

Using the priority list T4, T6, T5, T7, T8, T2, T1, T3, T9, schedule the project below with two processors.
Task Time Required Tasks that must be completed first
T16
T28
T35
T45
T57 T1
T65 T2, T3
T78 T4
T83 T5
T98 T5, T6
Task 5 is done by Incorrect starting at time Incorrect
Task 8 is done by Correct starting at time Incorrect
The finishing time for the schedule is Incorrect