Question: Using the priority list T 9 , T 1 , T 2 , T 4 , T 3 , T 6 , T 8 ,

Using the priority list T9,T1,T2,T4,T3,T6,T8,T5,T7, schedule the project below with two processors.
\table[[Task,Time Required,Tasks that must be completed first],[T1,2,],[T2,10,],[T3,4,],[T4,5,T1],[T5,9,T1, T2],[T6,4,T3],[T7,12,T5],[T8,10,T4, T5, T6],[T9,4,T5, T6]]
Task 6 is done by
starting at time
Task 7 is done by
starting at time
The finishing time for the schedule is