Question: Using the project information below and the least cost method, reduce the schedule until you reach the crash point of the network. For each move,

Using the project information below and the least cost method, reduce the schedule until you reach the crash point of the network. For each move, identify the activities crashed and the adjusted total cost. The initial project duration is 13 and the total direct cost is $1,000.

Activity

Duration

Predecessor

A

2x

None

B

3

A

C

6

B

D

4

B

E

3

D

F

1x

C and E

Activity

Slope

Maximum crash

Normal time

Normal cost

A

0

0

2

150

B

100

1

3

100

C

50

2

6

200

D

40

1

4

200

E

50

1

3

200

F

0

0

1

150

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!