Question: Using the replacement chain (common-life) approach, can you type the net present value of the project you would choose (A or B)? ..... Assume the
Using the replacement chain (common-life) approach, can you type the net present value of the project you would choose (A or B)? ..... Assume the discount rate is 5%. Year Project A -191,132 Project B -65,345 0 1 54,288 47,186 2 2. 54.220 47,765 3 52,355 4 55,708