Question: Using the same information: Activity Predecessor Normal Time Crash Time Normal Cost Crash Cost A - 4 3 100 350 B A 3 2 250

Using the same information:

Activity Predecessor Normal Time Crash Time Normal Cost Crash Cost
A - 4 3 100 350
B A 3 2 250 425
C A 2 2 400 400
D C 5 2 150 600
E B 3 3 325 325
F D, E 6 4 225 775
G D 4 2 175 925
H F, G 2 2 550 550

What is the shortest time to complete the project?

Group of answer choices

12 days

13 days

14 days

15 days

16 days

17 days