Question: Using the table: Activity Duration Immediate Predecessors A 4 - - - B 5 A C 6 A D 7 B , C E 6

Using the table:
Activity Duration Immediate Predecessors
A 4---
B 5 A
C 6 A
D 7 B,C
E 6 C
F 3 D,E