Question: Using the table below; 1)Draw the network 2)Identify the critical path 3)if activity E increased from 5 to 8 weeks, how does that change impact

Using the table below;

1)Draw the network

2)Identify the critical path

3)if activity E increased from 5 to 8 weeks, how does that change impact the project completion time, and does it change the critical path?

Activity Preceding Activity Time (weeks)
A - 4
B - 6
C A,B 7
D B 8
E B 5
F C 5
G D 7
H D,E 8
I F,G,H 4

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!