Question: Using the table below; 1)Draw the network 2)Identify the critical path 3)if activity E increased from 5 to 8 weeks, how does that change impact
Using the table below;
1)Draw the network
2)Identify the critical path
3)if activity E increased from 5 to 8 weeks, how does that change impact the project completion time, and does it change the critical path?
| Activity | Preceding Activity | Time (weeks) |
| A | - | 4 |
| B | - | 6 |
| C | A,B | 7 |
| D | B | 8 |
| E | B | 5 |
| F | C | 5 |
| G | D | 7 |
| H | D,E | 8 |
| I | F,G,H | 4 |