Question: Using the table below, answer the four questions. Days Activity a m b Immediate predecessors A 8 10 13 - B 6 7 8 -

Using the table below, answer the four questions.

Days

Activity

a

m

b

Immediate predecessors

A

8

10

13

-

B

6

7

8

-

C

3

3

6

B

D

10

18

28

A, C

E

6

7

8

C

F

9

10

11

D, E

G

5

7

11

A,D,E

H

15

16

17

F

I

10

13

15

F, G

J

6

7

8

G, H

K

4

7

10

I, J

L

1

3

6

G, H

(a=optimistic; m=most likely; b=pessimistic)

1. Using the network diagram, determine the EST, EFT, LST, LFT, slack time for each activity, critical path, and project completion time. 3. What is the probability that the project will be finished in 75 days? 4. What is a new expected completion time when the project needs to be done on time with the 90% probability.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!