Question: Using the table below, develop a resource plan and a schedule for the project cleaning and resupplying a passenger plane between flight legs. (Hint: Resource
- Using the table below, develop a resource plan and a schedule for the project "cleaning and resupplying a passenger plane between flight legs". (Hint: Resource Type could be cleaners, technicians, etc.)
- Which activities / operations are critical and why?
- Which resource type is the bottleneck?
| Activity | activity description | duration | predecessor | resource type |
| A | ||||
| B | ||||
| C | ||||
| D | ||||
| E | ||||
| F | ||||
| G | ||||
| H | ||||
| I | ||||
| J |