Using the table below, enter the activities, their durations (in days) and their relationships in Project 2016.
Fantastic news! We've Found the answer you've been seeking!
Question:
Using the table below, enter the activities, their durations (in days) and their relationships in Project 2016. Us a project start date of March 26, 2018. View the network diagram. Click the View tab and then click the Tables button under the Data group and then select Schedule. Make a few paragraphs explaining what the network diagram and schedule table show about Project X's schedule?
Activity | Initial Node | Final Node | Estimated Duration |
A | 1 | 2 | 2 |
B | 2 | 3 | 2 |
C | 2 | 4 | 3 |
D | 2 | 5 | 4 |
E | 3 | 6 | 2 |
F | 4 | 6 | 3 |
G | 5 | 7 | 6 |
H | 6 | 8 | 2 |
I | 6 | 7 | 5 |
J | 7 | 8 | 1 |
K | 8 | 9 | 2 |
Related Book For
Auditing A Practical Approach with Data Analytics
ISBN: 978-1119401742
1st edition
Authors: Raymond N. Johnson, Laura Davis Wiley, Robyn Moroney, Fiona Campbell, Jane Hamilton
Posted Date: