Question: Using the table below, enter the activities, their durations (in days) and their relationships in Project 2016. Us a project start date of March 26,

Using the table below, enter the activities, their durations (in days) and their relationships in Project 2016. Us a project start date of March 26, 2018. View the network diagram. Click the View tab and then click the Tables button under the Data group and then select Schedule. Make a few paragraphs explaining what the network diagram and schedule table show about Project X's schedule?

Activity Initial Node Final Node Estimated Duration
A 1 2 2
B 2 3 2
C 2 4 3
D 2 5 4
E 3 6 2
F 4 6 3
G 5 7 6
H 6 8 2
I 6 7 5
J 7 8 1
K 8 9 2

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!