Question: Using the table below, enter the activities, their durations (in days) and their relationships in Project 2016. Us a project start date of March 26,
Using the table below, enter the activities, their durations (in days) and their relationships in Project 2016. Us a project start date of March 26, 2018. View the network diagram. Click the View tab and then click the Tables button under the Data group and then select Schedule. Make a few paragraphs explaining what the network diagram and schedule table show about Project X's schedule?
| Activity | Initial Node | Final Node | Estimated Duration |
| A | 1 | 2 | 2 |
| B | 2 | 3 | 2 |
| C | 2 | 4 | 3 |
| D | 2 | 5 | 4 |
| E | 3 | 6 | 2 |
| F | 4 | 6 | 3 |
| G | 5 | 7 | 6 |
| H | 6 | 8 | 2 |
| I | 6 | 7 | 5 |
| J | 7 | 8 | 1 |
| K | 8 | 9 | 2 |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts