Question: Using the table below, perform the optimum resource smoothing (time constraint Scheduling)? Your solution should include both the Gantt chart view and histogram (bar chart)
Using the table below, perform the optimum resource smoothing (time constraint Scheduling)? Your solution should include both the Gantt chart view and histogram (bar chart) i.e. before and after resource smoothing Activities Predecessor Duration (Days) Resources (Designer) A Start 8 6 B A 4 4 C A 4 5 D A 5 2 E B 8 3 F B 2 3 G C,D,E,F 3 2