Question: using the time budget sheet shown, determine if this factory project will be on schedule. assume you are at the end of the 5th week
Week 11 12 13 14 15 16 17 2 3 4 5 6 7 8 9 10 7 7 7 7 7 7 7 4 3 2.625 4.375 7 7 1.625 5.375 1.625 4 1 CBC 1 Factory Setup 60 Hourly Employee 5.625 Training Salaried Employee 20 Training Order Ingredients 7 Inspect Ingredients 4 Ingred. Distr. Thru 1 Factory Equipment Cleaning | Equipment Inspection ? 1 Melting Sugar 1 Flavor Candy 1 Forming Shapes 0.25 Cool Down Period 1 Package 3 Inspection 3 Shipping 7 116.875 7 Cumulative 7 0.375 0.625 1 1 1 1 0.25 1 1.125 1.875 3 2.125 4.875 7 7 7 4.875 98 105 112 116.875 Total 7 7 7 7 7 7 7 7 7 14 21 28 35 42 49 56 63 70 7 7 7 77 84 91 Week 11 12 13 14 15 16 17 2 3 4 5 6 7 8 9 10 7 7 7 7 7 7 7 4 3 2.625 4.375 7 7 1.625 5.375 1.625 4 1 CBC 1 Factory Setup 60 Hourly Employee 5.625 Training Salaried Employee 20 Training Order Ingredients 7 Inspect Ingredients 4 Ingred. Distr. Thru 1 Factory Equipment Cleaning | Equipment Inspection ? 1 Melting Sugar 1 Flavor Candy 1 Forming Shapes 0.25 Cool Down Period 1 Package 3 Inspection 3 Shipping 7 116.875 7 Cumulative 7 0.375 0.625 1 1 1 1 0.25 1 1.125 1.875 3 2.125 4.875 7 7 7 4.875 98 105 112 116.875 Total 7 7 7 7 7 7 7 7 7 14 21 28 35 42 49 56 63 70 7 7 7 77 84 91
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts