Question: Using the weighted average method, what is the cost of closing work in process at 30 April. The following mfonnation peltains to operations for the

Using the weighted average method, what is the cost of closing work in process at 30 April.

The following mfonnation peltains to operations for the month of April: Work-in-Process, I Apr Units staffed April Umts convleted chu-i_ng Apnl Work-in-process, I April: IIIc-unai dunng April 16,000 100000 54,560 S35,560 $468,000 $574,040 Work-III-Process at I April was 600,' convlete for direct materials and 20% complete for conversion costs. Work-in-hceess at 30 April was complete for materials and 400/0 complete for conversion costs