Question: Using the weighted duration average of an activity based on the worst-case scenario, best-case scenario and most likely estimates means using Select one a. Parametric
Using the weighted duration average of an activity based on the worst-case scenario, best-case scenario and most likely estimates means using Select one a. Parametric estimating. b. Analogous estimating c. Bottom-up estimating d. Three point estimates