Question: Utilizing a decision tree, the NPV used to make the decision to commence the testing for a project is dependent on: only the cash flows
Utilizing a decision tree, the NPV used to make the decision to commence the testing for a project is dependent on: only the cash flows related to the actual test. on the path with the highest probability of occurrence. all project cash flows and probabilities over the projects entire life. only the cash flows and probabilities of the most successful path. all cash flows and probabilities for only the first year of the projects life.