Question: Utilizing another case study project, prepare a work package for direct labor for a system of work such as concrete foundations, CIP concrete walls,
Utilizing another case study project, prepare a work package for direct labor for a system of work such as concrete foundations, CIP concrete walls, tilt-up concrete walls, or SOG. Attach the original portion of the estimate that refers to this work package. B) As an alternate to a separate case study project, the following quantity and man-hour columns can be used as a baseline estimate. Assume a three-person crew working for four months from start to completion for all of these activities: Excavation: Formwork: Reinforcement steel or mesh: Concrete placement: Slab finish: 2 x 6 wall framing: Estimated quantities 100 CY 5,500 SF 30 Tons 400 CY 35,000 SF 33 MBF Estimated hours 100 550 300 200 350 500
Step by Step Solution
3.49 Rating (159 Votes )
There are 3 Steps involved in it
ANSWER This is a work package for direct labor for a system of work su... View full answer
Get step-by-step solutions from verified subject matter experts
