Question: uty: table [ [ Time of Day,Minimum No . of Officers on Duty ] , [ 8 : 0 0 a . m .

uty:
\table[[Time of Day,Minimum No. of Officers on Duty],[8:00 a.m.-noon,7],[Noon-4:00 p.m.,6],[4:00 p.m.-8:00 p.m.,9],[8:00 p.m.-midnight,7],[Midnight-4:00 a.m.,4],[4:00 a.m.-8:00 a.m.,6]]
etermine the number of police officers that should be scheduled to begin the 8-hour shifts atseach of the six times to minimize the total number of officers required. If your answer is zero, enter "0".
\table[[Starting Time,Officers Starting],[8:00 a.m.,],[Noon,],[4:00 p.m.,],[8:00 p.m.,],[Midnight,],[4:00 a.m.,]]