Question: uu llave tumpleted so far. It does not indicate Required information (The following information applies to the questions displayed below.] A manufactured product has the
uu llave tumpleted so far. It does not indicate Required information (The following information applies to the questions displayed below.] A manufactured product has the following information for June. Standard Actual 48,500 1bs. 8.10 per b. Direct materials Direct labor Overhead Units manufactured (6 lbs. $8 per lb.) (2 hrs. e $16 per hr15,700 hrs. $16.50 per hr. (2 hrs. $12 per hr-)$198,000 8,000 (1) Compute the standard cost per unit. Answer is complete and correct. Direc Direct labor Overhead Total t materials 48 32 24 $ 104