Question: v You The Agile team leader is considering developing the plan first and then including the project team. When considering leading and managing aglle project

v You
The Agile team leader is considering developing the plan first and then including the project team. When considering leading and managing aglle project teams, how is the project team involved in planning?
a. Provide no input.
b. Provide input on their portion of plan.
c. Collaboratively to minimize the budget.
d. Collaboratively and continually plan and commit.