Question: Vald E . Mort has been working a major project with numerous components. He decided to create a Gantt chart to help him manage the

Vald E. Mort has been working a major project with numerous components. He decided to create a Gantt chart to help him manage the many components of this project. Which item below will he NOT be able to easily determine by glancing at him Gantt Chart?
Question 2 options:
Critical Path
The start and end date of the whole project
The length of each activity
The start and end of each activity
Where activities overlap