Question: Vald E . Mort has been working a major project with numerous components. He decided to create a Gantt chart to help him manage the
Vald E Mort has been working a major project with numerous components. He decided to create a Gantt chart to help him manage the many components of this project. Which item below will he NOT be able to easily determine by glancing at him Gantt Chart?
Question options:
Critical Path
The start and end date of the whole project
The length of each activity
The start and end of each activity
Where activities overlap