Question: value: 5.00 points A project is expected to create operating cash flows of $25,000 a year for three years. The initial cost of the fixed

value: 5.00 points A project is expected to create operating cash flows of $25,000 a year for three years. The initial cost of the fixed assets is $52,000. These assets will be worthless at the end of the project. An additional $3,500 of net working capital will be required throughout the life of the project. What is the project's net present value if the required rate of return is 12 percent? O $1,958.33 O $7,037.01 $4,545.78 O $3,537.01 O $10,537.01