Question: value 5.00 points Compute the MIRR statistic for Project J if the appropriate cost of capital is 8 percent. (Do not round intermediate calculations. Round

value 5.00 points Compute the MIRR statistic for Project J if the appropriate cost of capital is 8 percent. (Do not round intermediate calculations. Round your final answer to 2 decimal places.) Project J Time: Cash flow 2 4 -$2,700 $860 $2,330 -$690 $810$270 MIRR Should the project be accepted or rejected? O Accepted O Rejected