Question: variable cost per unit is budgeted to be $6.00 and fixed cost per unit is budgeted to be $3.00 in a period when 5,000 units

variable cost per unit is budgeted to be $6.00 and fixed cost per unit is budgeted to be $3.00 in a period when 5,000 units are produced . If production is actually 4,500 units, what is the expected total cost of the units produced? A) $45,000 B) $40,500 C) $43,500 D) $42,000