Question: Variable Cost Variances The following data reflect the current months activity for Vickers Corporation: Actual total direct labor $655,200 Actual hours worked 37,700 Standard labor-hours
Variable Cost Variances
The following data reflect the current months activity for Vickers Corporation:
| Actual total direct labor | $655,200 |
| Actual hours worked | 37,700 |
| Standard labor-hours allowed for actual output (flexible budget) | 36,500 |
| Direct labor price variance | $23,400 F |
| Actual variable overhead | $157,120 |
| Standard variable overhead rate per standard direct labor-hour | $4.20 |
Variable overhead is applied based on standard direct labor-hours allowed.
Required
Compute the labor and variable overhead price and efficiency variances.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts