Question: Variables and Formulas WIDGET PRO: A product consisting of a base, a cover, a lens, and electronics. Statement of Work ( SOW ) : A

Variables and Formulas
WIDGET PRO: A product consisting of a base, a cover, a lens, and electronics.
Statement of Work (SOW): A document outlining the work to be done, including components and specifications.
Work Breakdown Structure (WBS): A hierarchical decomposition of the work required to complete a project.
Manufacturing Plan: A plan outlining the steps required to manufacture a product in a timely and efficient manner.
Test Equipment Work: The work required to test the WIDGET PRO units.
Concepts
WIDGET PRO Components: The base, cover, lens, and electronics that make up the WIDGET PRO.
Manufacturing Steps: The process of manufacturing the WIDGET PRO, including cutting, shaping, assembling, and testing.
Test Equipment Capacity: The maximum number of units that can be tested within a given time frame.
Main Body
Step 1: Develop the WBS
The WBS for the WIDGET PRO would include the following components:
Base 1.1. Cutting 1.2. Shaping 1.3. Finishing
Cover 2.1. Cutting 2.2. Shaping 2.3. Finishing
Lens 3.1. Cutting 3.2. Shaping 3.3. Finishing
Electronics 4.1. Assembly 4.2. Testing 4.3. Integration
Step 2: Manufacturing Plan
To manufacture 200 WIDGET PRO units without severely impacting the test equipment work, we propose the following plan:
Manufacture 50 units of the base, cover, and lens per day for 4 days.
Assemble the base, cover, and lens for 50 units per day for 4 days.
Integrate the electronics for 50 units per day for 4 days.
Test 50 units per day for 4 days.
This plan allows for a steady production rate of 50 units per day, while also allowing for adequate testing time.
Step 3: Reason for the Plan
The reason for this plan is to ensure a steady production rate while also allowing for adequate testing time. By manufacturing 50 units per day, we can ensure that the production line is running efficiently, while also avoiding a backlog of units waiting to be tested. By testing 50 units per day, we can ensure that the test equipment is not overloaded, which could lead to delays or errors in the testing process.
Final Answer
The WIDGET PRO Work Breakdown Structure (WBS) includes the following components: base, cover, lens, and electronics. To manufacture 200 WIDGET PRO units without severely impacting the test equipment work, we propose a plan to manufacture 50 units per day for 4 days, followed by assembly, integration, and testing of 50 units per day for 4 days. This plan ensures a steady production rate while also allowing for adequate testing time. give me references links to this topic?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!