Question: Variance analysis compare actual project results to planned or expected results in terms of cost, schedule, scope, quality, and risk. True False If the schedule
Variance analysis compare actual project results to planned or expected results in terms of cost, schedule, scope, quality, and risk.
True
False
If the schedule variance (SV) is > 0, then the Project Manager is in trouble/behind schedule.
True
False
The term for How much work should be accomplished at this time?" refers to the Planned Value (PV).
True
False
The term for How much work has been accomplished to date refers to the Earned Value (EV).
True
False
Earned value analysis integrates cost and schedule measures.
True
False