Question: Variance Analysis (Material and Labor): Calculate the material price variance, material quantity variance, labor rate variance, and labor efficiency variance for a manufacturing company, based
Variance Analysis (Material and Labor): Calculate the material price variance, material quantity variance, labor rate variance, and labor efficiency variance for a manufacturing company, based on the following data:
- Actual Material Price: $10 per unit
- Standard Material Price: $9 per unit
- Actual Material Quantity: 8,000 units
- Standard Material Quantity: 7,500 units
- Actual Labor Rate: $15 per hour
- Standard Labor Rate: $14 per hour
- Actual Hours Worked: 6,000 hours
- Standard Hours Allowed: 5,500 hours