Question: Vasquez Construction Materials Company has a payroll processing department. The payroll processing department is a cost center and prepares a monthly responsibility report. The following

Vasquez Construction Materials Company has a payroll processing department. The payroll processing department is a cost center and prepares a monthly responsibility report. The following information is provided. Cost Center Responsibility Report Flexible Budget Variance Wages Supplies Other Expenses Total Expenses Actual Results $33,800 38.190 40.300 Flexible Budget $37,000 33.000 40,000 What is the flexible budget variance for total expenses for the period? O A. $1,990 U OB. $2,290 U O C. $1,990 F OD. $2.290 F