Question: Vaughn Manufacturing is constructing a building. Construction began in 2 0 2 5 and the building was completed 1 2 / 3 1 / 2

Vaughn Manufacturing is constructing a building. Construction began in 2025 and the building was completed 12/31/25. Vaughn
made payments to the construction company of $3114000 on 71,$6456000 on 91, and $5950000 on 12/31. Weighted-average
accumulated expenditures were
$3709000.
$9570000
$3171000
$15520000
 Vaughn Manufacturing is constructing a building. Construction began in 2025 and