Question: ve an hour and a half to complete the assignment Question 1 In activity based costing, the total overhead cost in an activity cost pool
ve an hour and a half to complete the assignment Question 1 In activity based costing, the total overhead cost in an activity cost pool can be computed by: dividing the total activity in the activity cost pool by the activity rate for the activity cost pool. multiplying the total activity in the activity cost pool by the activity rate for the activity cost pool. dividing the total direct labor-hours in the activity cost pool by the activity rate for the activity cost pool. multiplying the total direct labor-hours in the activity cost pool by the activity rate for the activity cost pool