Question: Vell Incorporated uses lean principles to reduce cycle time. Through production improvements the process time was reduced from 4 . 5 days to 2 days.

Vell Incorporated uses lean principles to reduce cycle time. Through production improvements the process time was reduced from 4.5 days to 2 days. Inspection time is 0.25 days. Strategic rearrangement of the production area reduced move time to 0.1 days. Wait time was 3 days, but due to improved scheduling and ordering, it has been reduced by 2.25 days. Total cycle time for Vell after the improvements is: