This assignment must be completed and submitted using a Microsoft Excel spreadsheet xIs Provide a source for each equation you use. Sources must be listed at the bottom of the spreadsheet. No title page or additional formatting is required.
Channels of Communication
It has been estimated that project managers spend up to of their time communicating and your position at Roto Air is typical. Calculate the number of possible channels of communication if the project team were to grow to nine members, Important: show your work.
The total number of stakeholders, including the project team, is estimated at people. Calculate how many more possible channels of communication the additional
Launch External Tool
Previous
Next
Dashboard
Calendar
To Do
Notifications
Inbox
Verizon LTE
: PM
Assignment Details
BUS: Project Planning and Management MFXA
Benefit Cost Ratio BCR
Roto Air plans to spend $ on this project, resulting in a total savings of $ over the life of the project. Calculate the Benefit Cost Ratio. Important: show your work. Ignore any effects of the time value of money.
Roto Air also considered another project that would have partially satisfied their needs. It would have required a $ investment and would result in a savings of $ per year for years. Calculate the Benefit Cost Ratio. Important: show your work. Ignore any effects of the time value of money.
Comparing only the BCRs explain which project should Roto Air should have chosen. Ignore any effects of the time value of money.
Payback Period
Calculate the payback period for the $ investment shown above. Important: show your work. Ignore any effects of the time value of money.
Launch External Tool
Previous
Next
Dashboard
Calendar
To Do
Notifications
Inbox
Verizon LTE
: PM
Assignment Details
BUS: Project Planning and Management MFXA
Comparing only the BCRs explain which project should Roto Air should have chosen. Ignore any effects of the time value of money.
Payback Period
Calculate the payback period for the $ investment shown above. Important: show your work. Ignore any effects of the time value of money.
Calculate the payback period for the $ investment shown above. Important: show your work. Ignore any effects of the time value of money.
Comparing only on the payback periods, explain which project should Roto Air have chosen. Ignore any effects of the time value of money.
Net Present Value NPV
Calculate the Net Present Value of Roto Air's $ investment with a $ annual savings for years when the interest rate averages annually. Important: show your work.
Launch External Tool
Previous
Next
Dashboard
Calendar
To Do
Longrightarrow
Notifications
Inbox
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock