Question: View A process currently services an average of 53 customers per day Observation in recent weeks show that its utilization is about 90 percent, allowing

View A process currently services an average of
View A process currently services an average of 53 customers per day Observation in recent weeks show that its utilization is about 90 percent, allowing for just a 10 percent capacity cushion If demand is expected to be 70 percent of the current level in five years and management wants to have a capacity cushion of just 7 percent what capacity requirement should be planned? The needed capacity requirement is customers per day. (Enter your respanse rounded up to the next whole number SAT